Articles
"Manufacturers
Need to Look at Lean Construction" (c) Dennis Sowards, Industry Week,
May 5, 2008
Lean started in
manufacturing and has helped many companies achieve
greater productivity and reduce costs. However, there is
one opportunity that most manufacturing plants ignore
regarding applying Lean and it is now a great potential
for increasing profits and being more competitive. That
is Lean Construction.
Plant management often views the construction phase of a new plant start-up
or the remodel of an existing facility as a necessary evil. While the facility
is under construction, no revenue is coming in and many dollars are being spent.
Some self-manage the construction process while other plant managers look to a
general contractor and/or a construction manager to keep costs down and meet
schedule. All plant managers feel limited in how much they can reduce costs and
schedule without impacting quality. In fact, the traditional thinking in
construction is that one can only get two of the three factors of construction:
quality -- low cost -- fast schedule. If you want it built right and fast, you
must pay more. It is analogous to the mistaken thinking that higher quality
always cost more. The quality guru Philip Crosby proved the fallacy of that. Now
Lean is proving that you can build for less, faster and still maintain quality.
Everyone talks about improving productivity in construction and many think it
will come by new technology and better project management software. Others
preach working smarter not harder but only give pep talks for solutions. The
answer to improving construction productivity is not just in more software,
technology or motivation but also in Lean.
In the construction world, waste is rampant. One study found that 57% of the
crew's time on construction jobs is waste. Many in construction including plant
managers accept waste as a way of life. Lean attacks waste just as effectively
in construction as in manufacturing. Lean applications in construction are still
in its infancy but already there are successful examples to validate its
benefits. The common Lean tools most often used in construction are: the 5S's,
Kaizen, Value Stream Analysis and Kanban. A new tool has been developed
specifically for managing projects in a Lean way.
Boldt, a general contractor, headquartered in Wisconsin reported these
results on its first four pilot project using Lean techniques:
| Type of Project |
Estimated Budget |
Actual Budget |
Estimated Construction Time |
Actual Construction Time |
| Industrial |
$15M |
$15M |
6 months |
5 months |
| Correctional |
$18M |
$17M |
18 months |
14 months |
| Health Care |
$5M |
$4.6M |
18 months |
12 months |
The Grunau Co., a mechanical contractor also in Wisconsin, conducted a Kaizen
event in its tool room and realized a savings of about $40,000 in the
utilization of tools.
The Lean Construction Institute has developed a tool specific for applying
Lean to project management. It is called the Last Planner System (LPS). The
'Last Planner' in construction is the field supervisor who assigns work to the
crews. Effective planning leads to effective execution. The LPS out-performs
traditional project management methods by:
- Reducing variability common among construction work so that the work flows
from the completion of one task to another.
- Making work ready to be performed so crews can finish a task without
interruption, rework or remobilization.
- Holding weekly coordinating meetings where last planners (supervision)
make commitments to each other in support of the schedule. Planning is most
effective when there is reliability in the commitments of the various work
groups and trades.
- Managing the project through monitoring the plan's completion rate (PPC)
rather than the progress compared to schedule (effort). This creates a
learning process by investigating plan failures. PPC is the percent of plan
work actually completed in the measuring period, usually one week.
In 2001 the Lean Construction Institute published research that found, on
projects where PPC was greater than 50%, companies averaged a productivity
factor of 85% (meaning the projects averaged 15% under budget). Jobs with PPC
less than 50% averaged a 1.15 productivity factor (15% over budget). While the
research did not explain why the cut-off was at 50%, the data support the logic
that if more of the work is completed as planned, the crews will be more
productive.
Customers are beginning to recognize the value of Lean in the facilities they
are building, and are demanding that contractors use Lean approaches. The
Construction Users Roundtable (CURT), an organization made up of the major
manufacturing, production and utility companies in the USA, has recently
published the following regarding Lean:
CURT's Key Agents of Change: Education is key; There needs to be a
shift in everyone's way of thinking; LEAN targets the best workforce, forms
solid relationships and builds trust; Owner's must be the agents of change and
must demand change; and LEAN must become the new culture of the industry.
In referencing Lean activities, CURT "replaced the phrase 'LEAN Construction'
with 'LEAN Project Delivery' to emphasize how this management approach was not
limited to construction. Rather, it encompasses an alternative method of project
delivery that uses LEAN concepts and principles to guide a combination of new
and existing techniques for contracting, design and supply chain management, and
off-site and job-site assembly coordination."
Joe Gionfriddo, the Global Construction Process Owner for The Procter and
Gamble Co., sees LEAN Project Delivery as valuable because it:
- Provides a win-win opportunity from Owner through Construction to
Manufacturing. (Owner, Architect, Designer, Purchaser, Constructor and
Manufacturer)
- Helps define the supply chain and work process that we want to succeed
with improving and eliminating losses. It helps establish a global Project
Delivery supply chain.
He sees the main challenge for both manufacturing and the construction
industry to be a significant behavior change. He says, "There is not one silver
bullet. LEAN Project Delivery is a journey of continuous learning, piloting,
testing, assessing and improvement. It is not an overnight process change."
Manufacturing can realize lower construction costs and faster time to
production when LEAN Project Delivery is applied.
|